Upcoming parking lot and pathway surface treatment projects
Published on May 08, 2019
In order to preserve and maintain Town facilities and multi-use pathways, a contractor will be performing crack sealing and applying surface treatments to the following Town facilities and multi-use paths over the next two weeks. In some cases, this is a three-part process. The contractor will first crack seal the area and then go back later and apply a chip seal or surface treatment, followed up with striping.
This will affect you if you use the following parking lots of pathways:
-
James D. Kriegh Park / Oro Valley Aquatic Center parking lots
-
Tangerine multi-use path (From La Cañada Drive to Oracle Road)
-
Lambert Lane multi-use path (West of La Cañada Drive)
-
680 Calle Concordia (Oro Valley Public Works and Parks and Recreations building)
Safety
If you see parking lot or pathway closure signs in these areas, please avoid using the specified parking lot or pathway as the crack sealing and surface treatment materials can be hot and dangerous. In addition to avoiding the area with your vehicle, please do not walk, run, bike, or allow your children or pets on these areas while the work is underway.
Schedule
James D. Kriegh Park east parking lot (see Map 1 below)
Crack sealing - Thursday, May 9 and Friday May 10
Surface treatment - Tuesday, May 14, 24-hour closure
Striping - Sunday, May 19, completed by noon
Please note: The James D. Kreigh Park parking lots will be scheduled so that access to one of the parking lots will be available during the crack sealing process on May 9 and 10.
James D. Kriegh Park west parking lot (see Map 1 below)
Crack sealing - Thursday, May 9 and Friday, May 10
Surface treatment - Saturday, May 18, 24-hour closure
Striping - Sunday, May 19, completed by noon
Please note: the Tangerine multi-use pathway has been divided into three sections for this project.
Tangerine multi-use pathway - First Avenue to Oracle Road (see Map 2 below)
Crack sealing - Thursday, May 9 and Friday, May 10
Surface treatment - Wednesday, May 15, 24-hour closure
Striping - Monday, May 20, completed by noon
Tangerine multi-use pathway - Monterra Vista Drive to First Avenue (see Map 3 below)
Crack sealing - Thursday, May 9 and Friday, May 10
Surface treatment - Thursday, May 16, 24-hour closure
Striping - Monday, May 20, completed by noon
Tangerine multi-use pathway - La Cañada Drive to Monterra Vista Drive (see Map 3 below)
Crack sealing - Thursday, May 9 and Friday, May 10
Surface treatment - Friday, May 17, 24-hour closure
Striping - Monday, May 20, completed by noon
Lambert Lane multi-use pathway
No crack sealing needed
Surface treatment - Tuesday, May 14, 24-hour closure
Striping - Wednesday, May 15, completed by noon
680 Calle Concordia parking lot
Crack sealing - Thursday, May 9 and Friday, May 10
Surface treatment - Saturday, May 18, 24-hour closure
Striping - Sunday, May 19, completed by noon
Naranja Park
To assist with dust abatement, a contractor will be chip sealing a section of dirt road in Naranja Park on Thursday, May 9. This will not affect access to the multi-use fields, dog parks or archery range.
Map Attachment(, 0B)
Please travel, walk or bike safely in these areas!