Published on April 26, 2023
ORO VALLEY, Ariz. (April 26, 2023) – The Town of Oro Valley Public Works Department scheduled pavement preservation work in various neighborhoods within Oro Valley beginning May 1 through May 12 (weather permitting). Work is typically performed between the hours of 7 a.m. to 5 p.m. Each neighborhood and the dates scheduled for treatments are listed below.
The Town asks residents to plan ahead, observe posted traffic signs and yield to construction workers in the area. Treated roads cannot be driven on for 24 hours after work is finished. If a resident’s trash collection is scheduled for pickup during the project, an area just outside of the treatment zone will be provided to place trash receptacles for collection.
The Town’s Pavement Preservation Program is data driven. Roads that receive treatment are prioritized based on when they were last treated or constructed. Pavement preservation extends the pavement life and is far less expensive than replacing asphalt. This program is the reason Oro Valley continues to have some of the best roads in the region.
For frequently asked questions about the Pavement Preservation Program, click here. For questions about the May schedule, please call Public Works at 520-229-4850.
The following neighborhoods are scheduled to be treated.
La Cholla Estates
Monday, May 1
Wednesday, May 3
Rivers Edge and Cañada Del Oro Estates
Monday, May 8
Tuesday, May 9
Wednesday, May 10
Thursday, May 11
Rivers Edge 2
Rancho Vistoso Neighborhood 5
Thursday, May 4
Friday, May 12
Verch WayTuesday, May 2 and Thursday, May 4
Pebble Creek Drive from East of Flicker Way to Hidden Springs DriveTuesday, May 2 and Friday, May 5