Tangerine Rd at Rancho Vistoso Blvd - Safety Improvements

Case #: 
OV30 14/15 08
Construction of a right-in/right-out driveway from Tangerine into the commercial complex at the northeast corner of Tangerine and Rancho Vistoso.
Status: 
Active

 

The Town is making safety improvements to the right-of-way near Tangerine and First Ave./Rancho Vistoso Blvd. during the months of February and March.

Work will be performed by Borderland, Inc., and is scheduled to be completed by late March, 2020. There is one planned lane restriction late in construction that will impact westbound traffic on Tangerine (east of Rancho Vistoso/First) for 1 – 2 days; otherwise, all construction activities are planned to take place outside the travel lanes.

Please drive safely and obey all traffic signs and construction personnel at the site.

Thank you for your patience as we work to improve your roadways.

Estimated Start Date: 
early February, 2020
Estimated Completion Date: 
late March, 2020
Street(s) Affected or Property Location: 
Tangerine Rd at Rancho Vistoso Blvd
Contractor or Applicant: 
Borderland
Town staff contact: 
Engineering Division, 229-4894, jscott@orovalleyaz.gov