Fall 2019 Pavement Preservation

Case #: 
OV30 19/20 01
Status: 
Active

Surface treatments are scheduled to be applied to the following neighborhoods/subdivisions:

Copper Creek

Desert Vista

Rancho Catalina

Sunset Ridge 2

Vista del Oro Estates

This project has been advertised to contractors. It is tentatively scheduled for September - October, 2019. A more detailed schedule with exact dates will be available once a contractor has been selected.

Estimated Start Date: 
September 2019
Estimated Completion Date: 
October 2019
Engineer or Property Owner: 
Engineering Division, jscott@orovalleyaz.gov, 229-4894